Patel Agri Industries plans new distillery in Arawan

Patel Agri Industries is planning to set up a greenfield distillery in Arawan village in Nalanda district of Bihar. The project involves setting up of 200 klpd grain based distillery and a cogeneration power plant of 15 MW. The new facility will produce 100 klpd of ethanol. Land required for the project is around 9.84 acres.

The project cost is estimated at Rs. 2110 million.

As of August 2021, the project is in planning stage.

Project Location Arawan Village, Nalanda District,Bihar
Project Cost (in million) ₹2,110
Project Capacity 200 klpd
Project Status Planning
Commissioning Date

Company Profile : Patel Agri Industries Pvt Ltd